Bottom floor has been clad. Corner joins are done with a white silicon type adhesive and the joins and screw holes are done with the hebel adhesive. Top floor will be done this week when the scaffold goes up on Monday. They will then render from the top to bottom - 3 coats. Electrical work should start later this week and into next. Plaster is due to start on 25/11 and lock-up around then as well.