Saturday, 16 November 2013

Top floor Hebel and Some more internal work

Pretty rough weather last week put the hebel guys a bit behind but they should be done early this week and then the render starts. Doors have been installed to the laundry and garage into the house. No front door as yet. Internally, more plumbing has been done with internal drain, shower bases, bath frame for upstairs and spa downstairs. Small change to plans as they needed to put in a bulkhead to drain from the toilet in Jessica's ensuite so had to bring pipe through laundry, then over the kitchen window across the pantry and powder room.  This resulted in lower ceilings in both pantry and powder room by 300mm. No big deal as ceiling heights were already raised so they are back to 8'. As an appeasement PD are putting in three down lights over the kitchen sink in the bulkhead which will look good. Electrical work this week and plaster is due to start Monday week so progress still outstanding considering that the slab went down in the first week of October!