Getting close now. Electrical has all but been completed, just PowerPoints and lights in garage and outside plus a couple of data points to do inside. Will double check plans to ensure they are all there. Roller doors have been installed however they forgot to put the Perspex windows in the top panel which has been brought to their attention and will be rectified this week. Tiler starts Monday 24/2 and waterproofing around baths and showers was done Friday. Render needs to be completed out front as well. Had a few dramas with the cross over for driveway. There isn't enough gap between the footpath crossover and a Telstra pit. The pit needs to be removed. Whose fault and therefore job it is is still under conjecture. I feel that it is the developers problem as they didn't pick it up when the house plans were submitted. Anyway there are no cables through It yet so moving it shouldn't be a major hassle. Probably 4 weeks to go.