Wednesday, 4 December 2013

Plaster

Plaster started Monday and they had hung all the sheets on the walls and ceiling in two days! By the end of the week all the patching and cornice will be completed.  Carpenters then return to build the stairs and plasterers come back and plaster the outside of the stairs as well as the ceiling in the garage and alfresco.  Roof (sheets) goes on the garage and portico from tomorrow and the tiles will go on the Alfresco this week as well.  Tilers were there today putting on the sarking and battens.  Lock up probably early next week.  Still flying along!